B'ville sidewalk repairs continue

Phase two is underway for the village sidewalk repair and restoration project.

Village Engineer Tim Baker reported all sidewalks in phase one of the sidewalk repair project in Baldwinsville are completed and he hopes pouring for sidewalks in phase two (Route 48, Syracuse and Oswego streets) will be underway by the next village board meeting (Oct. 1). He noted there is some restoration work that still needs to be completed in phase one such as driveway work.